header image
Notice of Study Completion - Deseronto Stormwater Outfall

This notice issued March 2, 2017.
T. Trustham, Ecologist and Planner, Quinte Conservation

NOTICE OF STUDY COMPLETION

Schedule B Class Environmental Assessment

Deseronto Mill Pond – Stormwater Outfall Remediation

Town of Deseronto

The project aims to improve water quality using conventional approaches to treat the stormwater which currently drains, untreated, directly into the Mill Pond and then to the Bay of Quinte. The project is a cooperative effort between Environment Canada’s Great Lakes Sustainability Fund, Ministry of Environment’s Canada-Ontario Agreement for the Great Lakes, The Town of Deseronto, and the Quinte Conservation Authority. This project is being planned under Schedule B of the Municipal Class Environmental Assessment.

The decision matrix for the undertaking has determined that the use of an underground oil and grit separator unit will best address the concerns of the public while improving water quality within the Bay of Quinte.

Project plans and other information can be viewed at the following location:

Quinte Conservation

2061 Old Highway 2

Belleville, ON

K8N 4Z2

Monday to Thursday: 8:30am – 4:30pm

Friday: 8:30am to 4:00pm

Phone: (613) 968-3434

 

Interested persons should provide written comment to Quinte Conservation within 30 calendar days from the date of this Notice. Comment should be directed to:

Tim Trustham

Ecologist and Planner

Quinte Conservation

2061 Old Highway 2

Belleville, ON

K8N 4Z2

Phone: (613) 968-3434 ext. 110

Email: ttrustham@quinteconservation.ca

If concerns arise regarding this project which cannot be resolved in discussion with the Conservation Authority and the Town of Deseronto, a person or party may request that the Minister of the Environment make an order for the project to comply with Part II of the Environmental Assessment Act (referred to as a Part II Order), which addresses individual environmental assessments. Requests must be received by the Minister at the address below within 30 calendar days of this Notice. A copy of the request must also be sent to the Conservation Authority. If there is no request received by April 3, 2017 the project will proceed to design and construction as presented in the planning documentation.

Minister of the Environment

135 St. Clair Avenue, 10th Floor

Toronto, ON

M4V 1P5

 